LICONS Project:- Progress

The project activities commenced with a pre-project meeting at Oxford Brookes University, UK, on 31st May 2002, ahead of the contracted start date.

Progress at the time of updating this website is summarised below:

WORK PACKAGE A
Conceptual Design, Appraisal and System Characterisation

Task 1 – Appraisal and viability assessments
Subtasks initiated, under task leadership of TRADA Technology. Target for completion: Month 7, with any necessary modification in months 7-12.
Task 2 – Engineering and Materials Science Inputs
Subtasks initiated, under task leadership of Rotafix. Target for completion: Month 7 with any necessary supplementary tests concluded by month 12.
Task 3 – Definition / Modelling of Selected Configurations
Subtasks initiated, under task leadership of TRADA Technology. Target for completion: Month 7.
WORK PACKAGE B:
Design, Analysis and Testing

Task 4 - Design Optimisation
Subtasks due to commence in month 5, under task leadership of Oxford Brookes University. Target for completion: Month 12
Task 5 - Physical Testing and Prototyping
Preliminary phase of subtask 5.3 (Development of Structural Eurocode -type principles) initiated, under task leadership of TRADA Technology. Target for reporting: Month 12 with follow-on conclusion to testing subtask 5.2 by month 18.
WORK PACKAGE C:
Process Specifications

Task 6 – Development of Specifications and Quality Tools
Subtasks initiated, under task leadership of STAP. Target for completion: Month 14.
Work package D:
Execution and Fabrication

Task 7 – Procedures for Making Prefabricated Elements
Subtasks due to commence in month 9, under task leadership of LegnoDOC.
Task 8 – Procedures for Making Connections on Site
Subtasks initiated, under task leadership of Rotafix. Target for reporting: Month 18 with follow-on conclusion to subtasks 8.4 and 8.5 by month 23.
Task 9 – Real Life Case-Study Trials
Preliminary phase of subtasks initiated, under task leadership of ECC. Target for reporting: Month 18 with follow-on conclusion to subtasks by month 23.

Work package E:
Protection, Conservation, Cultural Measures and Knowledge Encapsulation

Task 10 – Documentation and Development of Computer Websites
Subtasks initiated, under task leadership of LegnoDOC.
First completed task is the production of the first version of this project website (June'02).

Task 11 – Knowledge Encapsulation, Dissemination and Training
Subtasks due to commence through later stages of the project, unifying the outputs from individual work tasks as they become available, under task leadership of Rotafix.

 

Any advice or methodology provided by LICONS contributors, reseracher or commercial member and/or any of its associated employees and agents is given in good faith but without warranty insofar as interpretation and use by a third party is beyond our control.